Daily Reports can only be accessed by Project Owner, Project Manager and Supervisors.
βGenerating a Daily project report
Go into the project you want a Daily Report from
If you have the correct role, you will see Project reports in the navigation menu on the left.
Click Project reports.
Select Project reports in the bottom-left of the Create Report section.
Choose Daily report.
Fill in any information you see fit. Empty fields are not included in the final report.
Click on Generate report.
Once generated, you can access the report in Project reports. You can also access any previously generated reports on this screen.
Download reports by clicking on the Titleof the report.
A Daily project report will include the following information if it was changed recently.
Important notes
Subcontractor notes
Project members on site
Project progress
Issues (With images)
Scope of Works (With images)
Tasks (With images)
Change requests
Documents
RFI
Submittals
Forms
Check-Ins
Because the Example project only had an RFI change on the day in question, the report looks like this: