What can I do with the Gantt View?
You can set planned start dates and due dates
You can update the item’s status (Open, In Progress, Complete, Verified)
You can set the responsible person
You can link items with predecessors and successors using standard dependencies:
“Finish to Start” - target task can’t start before the source task ends (but may start later)
“Start to Start” - target task can’t start until the source task starts (but may start later)
“Finish to Finish” - target task can’t end before the source task ends (but may end later)
“Start to Finish” - target task can’t end before the source task starts (but may end later)
You can use Auto-Scheduling to control planned start and finish dates
NOTE: If you use Gantt view to auto-schedule, you must change dates in the Gantt View to apply auto-scheduling to successor and predecessor items
You can mark the progress of an item (percent complete)
You can export a snapshot of the Gantt View to PDF or to Excel